Beckwith Street – Old Lock Bridge Rehabilitation

The construction of the new bridge deck has largely been completed with the exception of the paving transitions that will be completed on either side of the work zone in the spring of 2019.    The remaining works and associated schedules are listed as follows:

Week of December 3rd

Week of December 17th (weather permitting)

Spring of 2019 (approx. 3-5 days)

The construction of the Old Lock Bridge deck represents another significant investment in the Town’s roads and bridges through the support of over $1.21M in grants under the Provincial Connecting Links Program.     The Town is very pleased to report that, despite the onset of an early winter,  the new bridge will be delivered well within the forecasted budget of $1.77M.

For further information on the bridge project please contact the Public Works and Utilities Department at 613-283-4124 Ext. 3302